Manufacturing and instruments production facility with 250+ FTE. Project duration – 6 months.
Business process optimization, costs optimization and headcount right sizing. Personal areas of assignment were production, quality control, sales and marketing, procurement, R&D.
Analyzed existing processes and procedures in Production department:
- Planning, forecasting, control and evaluation methods;
- Management behavior;
- On-floor practices – materials availability, man-load planning and allocation, WIP, QC;
- Market and Strategy analysis in Sales – competitors, dealers, communication approach, segmentation, etc.;
- R&D analysis from idea to production approval.
>> Activities – performed man loading, ratio delay, variance study, scrap control and management, flexibility matrix and responsibility charts, bottleneck analysis, value stream mapping, line balance, capacity analysis, detailed observations.
- Validated, justified and agreed process requirements, improvement potentials and action measures in all departments;
- Re-designed, tested and deployed resource Master Schedule, which was later integrated into existing ERP;
- Implemented management tools and routines to engage active supervision;
- Outsourced non-typical activities;
- Agreed and applied measures towards reactivation in Sales & Marketing;
- Deployed Poka Yoke approach at key production spots allowing operators to evaluate if produced conforms with requirements.